News

Summary of September 16th and 17th public meetings

On September 16 and 17, residents of the Îles-de-la-Madeleine were invited to meet with the PEDGI project team to discuss the project’s progress and the different ways to get involved in the next steps.

A few people attended the meeting in Grosse-Île, providing an opportunity to speak with the project team. The meeting scheduled in Cap-aux-Meules could not take place due to a lack of participants.

We want to continue creating opportunities to engage with the community and raise awareness of the different ways to get involved. Although the project has received government authorization, not everything is set in stone. The community’s concerns, ideas, and local knowledge can still help improve the project.

The Working Group could not be formed as planned, but the seats reserved for community members remain open. Consultation efforts are continuing, notably through the Liaison Committee, to raise awareness of its role and provide opportunities to connect with you.

👉 Read the meeting summary and the project team’s responses: English summary

👉 You would like to get involved or learn more about the Working Group? Contact us at info@parceoliengrosseile.ca

News

Grosse-Île wind farm project: decree adopted and dialogue continues

Magdalen Islands, September 9, 2026 – A major milestone has been reached for the Grosse-Île wind farm project with the Quebec government’s adoption of a decree authorizing the project. Approved during the mid-August Cabinet meeting, this decree enables Nutrinor–Gilbert Énergies renouvelables and the Alliance de l’énergie de l’Est to initiate the steps required to obtain ministerial authorizations for the construction of four wind turbines. This government decision aligns with the findings of the BAPE  regarding the project’s significant and essential contribution to the energy transition and the decarbonization of the Îles-de-la-Madeleine, by reducing the annual consumption and transport of 11 million litres of fuel oil for the Cap-aux-Meules power plant. For the partners, this new stage reinforces a clear commitment : to maintain dialogue with the local community and continue refining the project in light of the concerns and expectations expressed.

Meeting local expectations

“Since the wind farm project began, several concrete actions have been implemented to ensure its harmonious integration into the existing environment. Key engagements include annual monitoring of the coastline and dune system, the implementation of resilience measures against coastal hazards, and various initiatives designed to foster and enhance the protection of local flora and birdlife,” noted Maxime Gilbert, General Manager of Nutrinor-Gilbert Énergies renouvelables.

“In the coming weeks and months, we will continue the enhancement work initiated during the BAPE hearings to better meet local expectations, notably through the implementation of a community engagement plan. Our goal remains the same: to evolve the project so it better aligns with the community’s expectations, while preserving its significant contribution to the energy transition and decarbonization of the Magdalen Islands,” Mr. Gilbert concluded.

“For several months, our team has been actively working to adjust various aspects of the project in response to concerns and expectations expressed by the community. Work has already been carried out to optimize turbine placement—such as producing new visual simulations from viewpoints important to the community—and to strengthen mechanisms for information sharing, dialogue, and citizen participation. This process is ongoing, aimed at incorporating feedback and improving the project based on the realities and concerns of Grosse-Île residents,” highlighted Simon Deschênes, Vice-President of Alliance de l’énergie de l’Est.

Significant benefits for the community

The Grosse-Île wind farm will reduce fuel oil consumption at the Cap-aux-Meules power plant by 11 million litres annually—equivalent to eliminating more than one oil tanker delivery per year. It also offers the potential to cut greenhouse gas emissions by 30,000 tonnes, the equivalent of taking approximately 10,000 cars off the road. Together, the Dune-du-Nord and Grosse-Île wind farms will save nearly 20 million litres of fuel annually by supplying over one-third of the archipelago’s electricity.

Beyond environmental benefits, the project would generate significant structural advantages for the community: 20 to 30 jobs at the peak of construction; estimated distributions of $22.5 million over 30 years to members of the *Alliance de l’énergie de l’Est*; and payments totaling over $1.7 million to the Municipality of Grosse-Île. Additional revenue linked to public land leases would also be paid to the *Communauté maritime des Îles-de-la-Madeleine*.

Meeting on September 16 in Grosse-Île.

The Grosse-Île wind farm project team continues its commitment to engaging with the Grosse-Île community. To this end, a meeting will be held on Wednesday, September 16, 2026, at 6:30 p.m. in the Grosse-Île gymnasium. The meeting aims to discuss the project and initiate the formation of a working group bringing together residents, local organizations, and project developers. This group will foster dialogue among stakeholders, help improve the project’s development, and ensure that its implementation takes into account local concerns and realities.

Residents and representatives of local organizations interested in joining this working group are invited to submit their applications by filling out the following form: https://fr.surveymonkey.com/r/PEDGI

Meeting on September 17 in Cap-aux-Meules

New citizen engagement initiatives are also planned for Cap-aux-Meules, with a meeting scheduled for Thursday, September 17, 2026, at 6:30 p.m. at the Cap-aux-Meules community hall, located at 460 Chemin Principal. This meeting will allow individuals from the *Communauté maritime* and Municipality of the Magdalen Islands who wish to get involved in the Grosse-Île wind farm liaison committee to learn more about the process, particularly regarding the addition of a citizen representative to the committee.

Those wishing to apply for the liaison committee can fill out the form at the following address: https://fr.surveymonkey.com/r/PEDGIFR

-30-

  Media contact :

Simon Falardeau, PRP, ARP
Nutrinor‑Gilbert Énergies renouvelables
514 755-5831
simon@simonfalardeau.ca

 

 

 

 

 

 

News

Project optimization: two turbine locations removed

No Comments

Grosse-Île Wind Farm project optimization: two turbine locations removed

Îles‑de‑la‑Madeleine, April 23, 2026 – Following ongoing discussions with host community stakeholders and organizations, recent public hearings held by the Bureau d’audiences publiques sur l’environnement (BAPE), and exchanges with Québec’s Minister of the Environment, the Fight Against Climate Change, Wildlife and Parks, Nutrinor–Gilbert Énergies renouvelables and l’Alliance de l’énergie de l’Est have jointly committed to removing two wind turbine locations from the Grosse-Île Wind Farm project in the Magdalen Islands. The two turbines locations initially planned for the southernmost sector of the site, on the lagoon side near Grand Étang (locations E6 and E7), will be withdrawn. This decision reflects the importance of protecting sensitive ecosystems and wetlands, preserving Conrad’s crowberry shrub habitats, considering the presence of potential habitats for the Horned Grebe, as well as addressing concerns raised by community members and environmental organizations.

“From the outset, our objectives have remained the same: to maximize positive benefits for the community while responding to local concerns related to renewable energy development and environmental impacts, all while meeting Hydro‑Québec’s contractual requirements. We are fully committed to a constructive, rigorous, and responsible process to develop a project that will be considered acceptable over the long term, economically, energetically, environmentally, and socially, by taking community input into account,” said Maxime Gilbert, general manager of Nutrinor‑Gilbert Énergies renouvelables.

Listening to concerns and adapting the project

Environmental organizations and local residents expressed concerns regarding the location of the two turbines initially planned for the southern lagoon-side sector, as well as the potential dispersion of the project across two sites.

“We continued our technical and environmental analyses in collaboration with the Minister of the Environment to optimize and reassess the turbine locations for the Grosse-Île Wind Farm, while carefully listening to the interventions of the citizens of the Magdalen Islands and organizations. These adjustments reflect the changes made and our genuine desire to design the best possible project. We remain committed to ongoing dialogue with the community,” added Simon Deschênes, vice president, Alliance de l’énergie de l’Est.

From the initial scenario to a reduced environmental footprint

The selection of turbine locations for this project is the result of more than 20 years of consultation efforts conducted in the Magdalen Islands. The site was identified and retained following rigorous analyses and consultations based on technical, environmental, and community integration criteria.

An environmental impact assessment was conducted using a maximum scenario of seven turbines. This approach made it possible to evaluate potential environmental effects comprehensively while maintaining flexibility in the final selection of turbine locations and models. The initial scenario included four proposed sites and three reserve sites, distributed across the northern (Gulf side) and southern (lagoon side) sectors.

With the removal of the two southern lagoon-side turbine locations near Grand Étang, the project confirms its intention to develop four wind turbines comparable in scale to those at the North Dune Wind Farm, located near the Mines Seleine port facilities and the Minister of Transport and Sustainable Mobility’s sand depot. This adjusted configuration is consistent with the project’s original objectives: delivering tangible benefits to the community, minimizing environmental impacts, and continuing to respond to stakeholder concerns.

Significant positive impacts

The Grosse-Île Wind Farm project fully aligns with Hydro‑Québec’s decarbonization action plan. It contributes directly to the energy transition while limiting its ecological footprint. The project would generate 16.8 megawatts (MW) of renewable energy for the local grid and allow 40% of the Islands’ electricity to come from renewable sources.

It would also help avoid the emission of approximately 30,000 tonnes of greenhouse gases per year on the Islands’ electricity network and reduce annual fuel oil consumption at the thermal power plant by 11 million litres.

— 30 —

Media Contacts :

 
Simon Falardeau, PRP, ARP

Nutrinor‑Gilbert Énergies renouvelables

514 755-5831

simon@simonfalardeau.ca

Lou Landry

Alliance de l’énergie de l’Est

581 886-3424

llandry@alliance-est.ca

News

Public information sessions in Fatima and Grosse-Île

The Bureau d’audiences publiques sur l’environnement (BAPE) invites the general population to public information sessions as part of the information period for the Grosse-Île Wind Farm Project (PEDGI) in the Magdalen Islands maritime community:

December 3, 2025 (7:00 p.m.): 4 chemin Ernest, Fatima and webcast
December 4, 2025 (7:00 p.m.): 1-006 chemin Jerry, Grosse Île

After two years of refining the project and its impact assessment, the PEDGI team is pleased to present the project details to the community of Grosse-Île and, more broadly, the Magdalen Islands. These sessions are an opportunity for the community and interested individuals to learn more about the project and the impact assessment conducted by the PEDGI team.

For all documentation on the project, please consult the website of the Bureau d’audiences publiques sur l’environnement.

News

Open House Information Session

No Comments

La séance d’information s’est tenue sous la forme de portes ouvertes. À cette occasion, nous avons présenté les mises à jour du projet et les mesures particulières qui vont être mises en place pour éviter, réduire et compenser les impacts sur l’environnement. Nous en avons profité également pour informer la population du calendrier et des différentes étapes qui mèneront à la mise en service du parc éolien en octobre 2025. Des membres de l’équipe de Parc éolien de Grosse-Île seront sur place pour répondre aux questions du public.

News

Electricity supply contract signed

No Comments

Signature du CONTRAT D’APPROVISIONNEMENT EN ÉLECTRICITÉ entre Parc Eolien de Grosse-Île S.E.C et Hydro-Québec, dans ses activités de distribution d’électricité.

Toute l’électricité produite par le parc éolien et livrée au point de livraison est vendue en exclusivité au Distributeur.

Durée du contrat : Sous réserve des conditions qui y sont prévues, le contrat est en vigueur à compter de la date de sa signature et il se termine après qu’il se soit écoulée une période de 30 ans, débutant à la date du début des livraisons.