KEY MILESTONES IN THE PROJECT’S DEVELOPMENT:
2007
The Agglomeration of the Îles-de-la-Madeleine establishes a Consultative Commission on Wind Development and conducts a public consultation.
2010
The Municipality of the Îles-de-la-Madeleine designates land for industrial use related to wind energy production and helps found the Alliance, a regional energy board.
2012
The Municipality designates the Dune-du-Nord sector as an industrial zone for wind energy production.
2015
Hydro-Québec issues a call for proposals to select a private partner to co-develop the Dune-du-Nord site alongside the Alliance.
2016
The Maritime Community conducts a public consultation to adopt a territorial energy strategy.
2022
The Grosse-Île Wind Farm project is launched, and the first public consultation is held by the project developers.
2023
A Power Supply Agreement is signed between Hydro-Québec, the Alliance de l’énergie de l’Est, and Valeco Énergie Québec for a contracted capacity of 16.8 MW of wind energy in the Îles-de-la-Madeleine.
Nutrinor-Gilbert Énergies renouvelables acquires Valeco Énergie Québec.
2025
Beginning of the public hearings period for the Bureau d’audiences publiques sur l’environnement (BAPE).
